We’re making multiple copies of the BE-4 to take us through our development campaign, along with a healthy amount of hardware spares to mitigate schedule and technical risks encountered along the way - - a “hardware rich” approach to development. To maintain a fast pace, we’ve elected over the past years to invest heavily in key machines, tooling and people for the production of BE-4 so we can control critical processes in-house.Image
Beginning to slot one of our nozzles

Image

Image
Main propellant valve machining

Image
Preparing inspected GOx dome casting for machining

We’ve also started testing the BE-4 preburner in our recently commissioned pressure-fed test cell. We’re developing the transient start sequence for the preburner, and we’re making good progress
Image
Hot firing a 14” diameter preburner

#2 Re: Blue Origins update

Posted: Fri, 17 Jun 16, 14:35 pm
by Joe Wooten
It is great to see private companies at work on stuff without major government involvement.....